The Streamwood Park District undertook a multi-year, comprehensive renovation of its Community Center, a facility that has served the community for nearly 50 years.

Rather than pursuing a single large capital campaign, the district took a phased approach, completing improvements progressively as funding became available.

The renovation touched every aspect of the facility, from the roof to the gymnasium floor, ensuring the building is modernized and ready to serve future generations of Streamwood residents.

Key Features

Roof Replacement

Complete removal of existing roofing with new insulation and flat roofing materials installed in 2022.

Gymnasium Upgrades

New FieldTurf synthetic grass surface suitable for soccer, batting practice, flag football, and volleyball.

Solar Panel Installation

Environmentally-friendly solar panels expected to reduce energy costs by approximately 30%.

Interior Modernization

Elevator installation, viewing rooms, fresh wall paint, and new flooring throughout.

Project Timeline

2020

Renovation Planning Begins

District initiates comprehensive facility assessment

2022

Roof Replacement

Full roof removal and replacement with new materials

March 2022

Gymnasium Surface Installation

New FieldTurf synthetic grass surface installed

December 2022

Solar Panels Activated

Environmental solar panels begin reducing energy costs

2023

Interior Renovations Complete

Elevator, viewing rooms, and flooring projects finished