Aquatic Center Pool Renovation

Transparency

Comprehensive renovation of the aquatic center pools including resurfacing the lap and activity pools with DiamondBrite finishing and complete replacement of the spa pool.

Park Place Aquatic Center Pool Renovation
Park Place Aquatic Center Pool Renovation
Budget

$350,000

Grant Funding

$300,000 from Illinois DCEO

Timeline

Completion: Summer 2026

Overview

The Streamwood Park District is undertaking a comprehensive renovation of the Park Place Aquatic Center pools to ensure the facility continues to serve the community for years to come.

The 25-year-old spa pool required complete replacement after engineers discovered a leak in the jet line system. Rather than attempt costly repairs to an intricate 90-degree angled pipe configuration, officials determined full replacement was more fiscally responsible.

The project also includes resurfacing the lap and activity pools with durable DiamondBrite finishing material, providing a modern, long-lasting surface for swimmers of all ages.

Key Features

Lap and Activity Pools Resurfacing

Complete resurfacing with DiamondBrite finishing material, providing a durable, attractive surface that will last for years.

Spa Pool Replacement

Full demolition and reconstruction of the spa pool with new jet line system and modern infrastructure.

State-of-the-Art Engineering

Professional designs developed by WT Aquatic Engineering with all necessary Illinois Department of Public Health permits obtained.

Grant Funding Support

Secured $300,000 in state funding through the Illinois DCEO with assistance from State Representative Fred Crespo.

Project Timeline

January 2024

Lap and Activity Pools Completed

Successfully resurfaced with DiamondBrite finishing material

April 2024

Spa Pool Demolition Completed

Old spa pool and jet line system removed

Summer 2026

Spa Pool Reconstruction Complete

New spa pool with modern infrastructure ready for use

Funding Details

Illinois DCEO

$300,000

State grant funding secured with assistance from State Representative Fred Crespo

Streamwood Park District

$50,000

District funding to complete the project

Questions About This Project?

Contact our team for more information about project timelines, funding, or community impact.