Park Place Tot Lot Playground Renovation

a playground with a red slide and benches

The Streamwood Park District recently received a $200K grant from the Illinois Department of Commerce and Economic Opportunity (DCEO) to replace the “tot lot” playground located just outside the preschool wing at Park Place Family Recreation Center in partnership with RUSH Physical Therapy, 550 S. Park Blvd.

Here is a tentative project timeline:

  • 10/31/24:  Construction fencing will be installed at Park Place Tot Lot.
  • 11/4/24:  The old playground equipment and mulch will be excavated and removed from the site.
  • 11/6/24:  The new concrete curb will be installed.
  • 11/13/24:  The new playground equipment is scheduled to arrive and be installed.
  • 11/25/24:  The new poured-in-place artificial surfacing is scheduled to be installed.
  • Spring 2025:  New fencing, benches, and more!

Please stay tuned to this page for the latest updates on this project.

CONNECT

Stay in the Know

News & Updates

Stay informed about upcoming events, program changes, and the latest news from Streamwood Park District.

Community impact

Dive Deeper


Dive deeper into our impact with our comprehensive annual report, featuring detailed metrics, financial information, and program highlights.

SUBSCRIBE

Stay Updated

Stay connected with the latest news, events, and program updates from Streamwood Park District. Sign up for our newsletter today.